Hi,
My Guess was correct. There is an entry of KBUD for FY2002 in the BPJA table.
Here are my guesses in the steps followed previously, please correct if I am wrong:
- The WBS Element has cost planned using CJR2/CJ40 (Evident from KSTP)
- The Cost Planned has been copied to the Budget.
- Similar steps has been carried out for FY2002.
My proposed solution:
- Remove the Planned cost for all the years if possible.
- Else Reduce the plan cost in 2002 as Zero.
- Then copy the plan cost to budget using CJ30. (Assuming no Assigned values to this WBS as of now)
- Rebudget WBS as per the requirement.
Hope it helps!
Thanks and Regards,
Varshal Kachole