Re: Overall budget less than cumulative budget

$
0
0

Hi,

 

My Guess was correct. There is an entry of KBUD for FY2002 in the BPJA table.

 

Here are my guesses in the steps followed previously, please correct if I am wrong:

  • The WBS Element has cost planned using CJR2/CJ40 (Evident from KSTP)
  • The Cost Planned has been copied to the Budget.
  • Similar steps has been carried out for FY2002.

 

My proposed solution:

  • Remove the Planned cost for all the years if possible.
  • Else Reduce the plan cost in 2002 as Zero.
  • Then copy the plan cost to budget using CJ30. (Assuming no Assigned values to this WBS as of now)
  • Rebudget WBS as per the requirement.

 

Hope it helps!

 

Thanks and Regards,

Varshal Kachole