Dear gurus,
i had a scenario where semi finished material is combination of different batches,for production of semi finished material i had 6 operations in which up to 3rd operation i have 3 production lines in which each batch in the line is identified by different batch no and in 4th operation all batches are mixed and if new batch is coming into 4th operation the material which is already in 4th operation enters 5th&6th operation continously for semi finished material and enters remaining operations for finished material production .semifinished material is not stored in any place it is continously flow from 6th operation which is semi finished material to another operation which is used for producing finished material.
suppose for week i require 100 m3 of finished material , and for each batch i can produce 2 m3 in each production line ,i require 50 batches for week .the production is continous .
can i follow by creating 50 production orders each of different batch ,by creating semi finished material in 4th operation , can any one please suggest .